Q1 2025 – Completed Improvement Project

Goal: Implement 5S and improve material flow in the Kits Department.

Main result: Annual output increased by 5.4%, or 5,676 additional assembled units.

Q2 · 2025

Q2 2025 – Completed Improvement Project

Goal: Implement 5S and improve the value-added flow in the Electric Motors unit.

Main result: Lead time fell from 696 h to 528 h.

Q3 · 2025

Q3 2025 – Completed Improvement Project

Goal: Implement 5S and Lean principles in the Cylinders unit.

Main result: The 5S audit score rose from 50 to 97 points.

Q4 · 2025

Q4 2025 – Completed Improvement Project

Goal: Implement 5S and Kaizen in the Warehouse Department to optimize space and avoid unnecessary costs.

Main result: Future costs of €50,000 were avoided.