Linamar Light Metals Ruse Ltd.

2026

Q1 · 2026

Reducing overall scrap

Goal: Reduce overall scrap in the core-making area from 27% in 2025 to 22% by the end of Q1 2026.

Main result: Overall scrap fell from 27% to 26% in Q1 2026; digital scrap registration and analysis were introduced.

Q2 · 2026

Q2 2026 – Improvement Project

Goal: Reduce overall core-making scrap through better defect visibility, registration and analysis.

Main result: Overall scrap fell to 20% in Q2 2026, reaching the target.

Q3 · 2026

Q3 2026 – Improvement Project

Goal: Reduce core-making scrap from 27% in 2025 to 18% in Q3 2026, towards the annual target of 15%.

Main result: Overall scrap fell from 27% to 18%, reaching the Q3 2026 target.