Q1 2025 – Completed Improvement Project
Goal: Increase equipment availability through Autonomous Maintenance.
Main result: Equipment availability increased by more than 3%; 20% of the 2025 Autonomous Maintenance plan was completed.
LEAN CHAMPIONS
Presentations are available only to authorized users.

Goal: Increase equipment availability through Autonomous Maintenance.
Main result: Equipment availability increased by more than 3%; 20% of the 2025 Autonomous Maintenance plan was completed.
Goal: Implement the annual Autonomous Maintenance plan and improve 5S in the maintenance workshop.
Main result: The team did not attend the Q2 meeting; the results will be presented at the Q3 meeting.
Goal: Implement Autonomous Maintenance Steps 1–3 around the HC5FW line.
Main result: The 5S audit score rose from 88 to 95 points.
Goal: Improve the LFxx10 layout through 5S and Kaizen to free 95 m² and prepare for new product transfers in 2025–2026.
Main result: Approximately 95 m² of production space was freed up.